2020 Resurfacing Projects

The 2020 Street Resurfacing Project, funded by SPLOST and LMIG funds at $4.96 million,  will pave approximately 15.5 miles of Stonecrest's worst roads, including the following major thoroughfares:

  • Browns Mill Ferry Road (approx. 1 mile from Browns Mill Rd to dead end)
  • Phillips Road (approx. 0.75 miles between Covington Hwy and Marbut Rd)
  • Fairington Road (the entire 1.7 miles between Panola Rd and Hillandale Rd)
  • Mall Parkway (approx. 1.3 miles between Klondike and Evans Mill Rd)
  • Panola Road (approx. 1.4 miles between Snapfinger and Browns Mill Rd)
  • Rock Springs Road (approx. 1.1 miles between Cleveland Rd and Panola Rd)
  • Evans Mill Road (approx. 2.9 miles from Rock Spring Rd to Browns Mill Rd)

Additionally, the city will pave 3 subdivisions that were abandoned by the builders before the roads were completed:

  • Haynes Park
  • Terrace at Stonecrest
  • Miller Park (Lacy Lane and Tadmore Lane)

The paving contract was awarded to ER Snell Contracting and work is scheduled to begin the week of April 20, 2020. Click here for the 2020 Road Resurfacing List

Roadwork Updates

  • The paving crew will mobilize to Regency Park subdivision on Monday, June 22nd with a day crew.
  • The paving crew is also are putting out message boards on Fairington Road notifying the public of the paving operations will begin Wednesday night, June 17th.
  • Going forward, all major roads on the list will be done using a night paving crew

The following road(s) are scheduled for repaving during the week of:  June 8, 2020 :

  • Regency Park Drive
  • Alpine Court
  • Hardin Court
  • Aberdeen Way
  • Aberdeen Cove
  • Regency Forest Court
  • Regency Manor Court

View the 2020 Road Resurfacing list here:  